RecalculateResourceStartFinish

Project.RecalculateResourceStartFinish method

Recalculates Start and Finish of resources.

public void RecalculateResourceStartFinish()

Examples

Shows how to recalculate resource start/finish dates.

var project = new Project
{
    CalculationMode = CalculationMode.None
};

var task = project.RootTask.Children.Add("Task");
task.Set(Tsk.Start, new DateTime(2020, 3, 26, 8, 0, 0));
task.Set(Tsk.Duration, project.GetDuration(1d, TimeUnitType.Day));
task.Set(Tsk.Finish, new DateTime(2020, 3, 26, 17, 0, 0));

var resource = project.Resources.Add("Res1");
resource.Set(Rsc.Start, new DateTime(2020, 3, 26, 8, 0, 0));
resource.Set(Rsc.Finish, new DateTime(2020, 3, 26, 17, 0, 0));

var resourceAssignment = project.ResourceAssignments.Add(task, resource);
resourceAssignment.Set(Asn.Start, new DateTime(2020, 3, 25, 8, 0, 0));
resourceAssignment.Set(Asn.Finish, new DateTime(2020, 3, 27, 8, 0, 0));

Console.WriteLine("Resource Start (before): " + resource.Get(Rsc.Start));
Console.WriteLine("Resource Finish (before): " + resource.Get(Rsc.Finish));

// Recalculates Start and Finish of resources
project.RecalculateResourceStartFinish();

Console.WriteLine("Resource Start (after): " + resource.Get(Rsc.Start));
Console.WriteLine("Resource Finish (after): " + resource.Get(Rsc.Finish));

See Also