UpdateProjectWorkAsComplete

UpdateProjectWorkAsComplete(DateTime, bool)

Updates all work as complete through a specified date for the entire project.

public void UpdateProjectWorkAsComplete(DateTime completeThrough, 
    bool setZeroOrHundredPercentCompleteOnly)
ParameterTypeDescription
completeThroughDateTimeThe date to update work as completed through.
setZeroOrHundredPercentCompleteOnlyBooleanIf set to true updates only those tasks as 100% complete whose finish date is before specified complete-through date. Otherwise, calculates a percentage complete value based on scheduled start and complete-through dates.

Examples

Shows how to update the project and reschedule uncompleted work.

var project = new Project();
project.Set(Prj.StartDate, new DateTime(2014, 1, 27, 8, 0, 0));

// Add new tasks
var task1 = project.RootTask.Children.Add("Task 1");
var task2 = project.RootTask.Children.Add("Task 2");
task2.Set(Tsk.Duration, task2.ParentProject.GetDuration(16, TimeUnitType.Hour));
var task3 = project.RootTask.Children.Add("Task 3");
task3.Set(Tsk.Duration, task2.ParentProject.GetDuration(24, TimeUnitType.Hour));
var task4 = project.RootTask.Children.Add("Task 4");
task4.Set(Tsk.Duration, task2.ParentProject.GetDuration(16, TimeUnitType.Hour));
var task5 = project.RootTask.Children.Add("Task 5");
task5.Set(Tsk.Duration, task2.ParentProject.GetDuration(16, TimeUnitType.Hour));

// Add links between tasks
project.TaskLinks.Add(task1, task2, TaskLinkType.FinishToStart);
var link23 = project.TaskLinks.Add(task2, task3, TaskLinkType.FinishToStart);

// One day lag
link23.LinkLag = 4800;
project.TaskLinks.Add(task3, task4, TaskLinkType.FinishToStart);
project.TaskLinks.Add(task4, task5, TaskLinkType.FinishToStart);

// Add new tasks
var task6 = project.RootTask.Children.Add("Task 6");
var task7 = project.RootTask.Children.Add("Task 7");
task7.Set(Tsk.Duration, task7.ParentProject.GetDuration(24, TimeUnitType.Hour));
var task8 = project.RootTask.Children.Add("Task 8");
task8.Set(Tsk.Duration, task2.ParentProject.GetDuration(16, TimeUnitType.Hour));
var task9 = project.RootTask.Children.Add("Task 9");
task9.Set(Tsk.Duration, task2.ParentProject.GetDuration(16, TimeUnitType.Hour));
var task10 = project.RootTask.Children.Add("Task 10");

// Add links between tasks
project.TaskLinks.Add(task6, task7, TaskLinkType.FinishToStart);
project.TaskLinks.Add(task7, task8, TaskLinkType.FinishToStart);
project.TaskLinks.Add(task8, task9, TaskLinkType.FinishToStart);
project.TaskLinks.Add(task9, task10, TaskLinkType.FinishToStart);
task6.Set(Tsk.IsManual, true);
task7.Set(Tsk.IsManual, true);
task8.Set(Tsk.IsManual, true);
task9.Set(Tsk.IsManual, true);
task10.Set(Tsk.IsManual, true);

// Save project before and after updating work as completed 
project.Save(OutDir + "RescheduleUncompletedWork_not updated_out.xml", SaveFileFormat.Xml);

// Save project after updating project work as complete only for specified tasks
project.UpdateProjectWorkAsComplete(new DateTime(2014, 1, 28, 17, 0, 0), false, new List<Task> { task10 });
project.Save(OutDir + "RescheduleUncompletedWork_specific_updated_out.xml", SaveFileFormat.Xml);

// Save project after updating all project work as complete
project.UpdateProjectWorkAsComplete(new DateTime(2014, 1, 28, 17, 0, 0), false);
project.Save(OutDir + "RescheduleUncompletedWork_updated_out.xml", SaveFileFormat.Xml);

// Save project after rescheduling uncompleted work only for specified tasks
project.RescheduleUncompletedWorkToStartAfter(new DateTime(2014, 2, 8, 8, 0, 0), new List<Task> { task10 });
project.Save(OutDir + "RescheduleUncompletedWork_specific_rescheduled_out.xml", SaveFileFormat.Xml);

// Save project after rescheduling uncompleted work
project.RescheduleUncompletedWorkToStartAfter(new DateTime(2014, 2, 7, 8, 0, 0));
project.Save(OutDir + "RescheduleUncompletedWork_rescheduled_out.xml", SaveFileFormat.Xml);

See Also


UpdateProjectWorkAsComplete(DateTime, bool, List<Task>)

Updates all work as complete through a specified date for the specified list of tasks.

public void UpdateProjectWorkAsComplete(DateTime completeThrough, 
    bool setZeroOrHundredPercentCompleteOnly, List<Task> taskCollection)
ParameterTypeDescription
completeThroughDateTimeThe date to update work as completed through.
setZeroOrHundredPercentCompleteOnlyBooleanIf set to true updates only those tasks as 100% complete whose finish date is before specified complete-through date. Otherwise, calculates a percentage complete value based on scheduled start and complete-through dates.
taskCollectionList`1List<Task> of tasks to update work for.

Examples

Shows how to update the project and reschedule uncompleted work.

var project = new Project();
project.Set(Prj.StartDate, new DateTime(2014, 1, 27, 8, 0, 0));

// Add new tasks
var task1 = project.RootTask.Children.Add("Task 1");
var task2 = project.RootTask.Children.Add("Task 2");
task2.Set(Tsk.Duration, task2.ParentProject.GetDuration(16, TimeUnitType.Hour));
var task3 = project.RootTask.Children.Add("Task 3");
task3.Set(Tsk.Duration, task2.ParentProject.GetDuration(24, TimeUnitType.Hour));
var task4 = project.RootTask.Children.Add("Task 4");
task4.Set(Tsk.Duration, task2.ParentProject.GetDuration(16, TimeUnitType.Hour));
var task5 = project.RootTask.Children.Add("Task 5");
task5.Set(Tsk.Duration, task2.ParentProject.GetDuration(16, TimeUnitType.Hour));

// Add links between tasks
project.TaskLinks.Add(task1, task2, TaskLinkType.FinishToStart);
var link23 = project.TaskLinks.Add(task2, task3, TaskLinkType.FinishToStart);

// One day lag
link23.LinkLag = 4800;
project.TaskLinks.Add(task3, task4, TaskLinkType.FinishToStart);
project.TaskLinks.Add(task4, task5, TaskLinkType.FinishToStart);

// Add new tasks
var task6 = project.RootTask.Children.Add("Task 6");
var task7 = project.RootTask.Children.Add("Task 7");
task7.Set(Tsk.Duration, task7.ParentProject.GetDuration(24, TimeUnitType.Hour));
var task8 = project.RootTask.Children.Add("Task 8");
task8.Set(Tsk.Duration, task2.ParentProject.GetDuration(16, TimeUnitType.Hour));
var task9 = project.RootTask.Children.Add("Task 9");
task9.Set(Tsk.Duration, task2.ParentProject.GetDuration(16, TimeUnitType.Hour));
var task10 = project.RootTask.Children.Add("Task 10");

// Add links between tasks
project.TaskLinks.Add(task6, task7, TaskLinkType.FinishToStart);
project.TaskLinks.Add(task7, task8, TaskLinkType.FinishToStart);
project.TaskLinks.Add(task8, task9, TaskLinkType.FinishToStart);
project.TaskLinks.Add(task9, task10, TaskLinkType.FinishToStart);
task6.Set(Tsk.IsManual, true);
task7.Set(Tsk.IsManual, true);
task8.Set(Tsk.IsManual, true);
task9.Set(Tsk.IsManual, true);
task10.Set(Tsk.IsManual, true);

// Save project before and after updating work as completed 
project.Save(OutDir + "RescheduleUncompletedWork_not updated_out.xml", SaveFileFormat.Xml);

// Save project after updating project work as complete only for specified tasks
project.UpdateProjectWorkAsComplete(new DateTime(2014, 1, 28, 17, 0, 0), false, new List<Task> { task10 });
project.Save(OutDir + "RescheduleUncompletedWork_specific_updated_out.xml", SaveFileFormat.Xml);

// Save project after updating all project work as complete
project.UpdateProjectWorkAsComplete(new DateTime(2014, 1, 28, 17, 0, 0), false);
project.Save(OutDir + "RescheduleUncompletedWork_updated_out.xml", SaveFileFormat.Xml);

// Save project after rescheduling uncompleted work only for specified tasks
project.RescheduleUncompletedWorkToStartAfter(new DateTime(2014, 2, 8, 8, 0, 0), new List<Task> { task10 });
project.Save(OutDir + "RescheduleUncompletedWork_specific_rescheduled_out.xml", SaveFileFormat.Xml);

// Save project after rescheduling uncompleted work
project.RescheduleUncompletedWorkToStartAfter(new DateTime(2014, 2, 7, 8, 0, 0));
project.Save(OutDir + "RescheduleUncompletedWork_rescheduled_out.xml", SaveFileFormat.Xml);

See Also