RescheduleUncompletedWorkToStartAfter

RescheduleUncompletedWorkToStartAfter(DateTime)

Reschedules uncompleted project work to start after a specified date.

public void RescheduleUncompletedWorkToStartAfter(DateTime after)
ParameterTypeDescription
afterDateTimeThe date to reschedule uncompleted work after.

Remarks

Ensure that Project.CanSplitsInProgressTasks flag is set to true before using this method.

Examples

Shows how to update the project and reschedule uncompleted work.

var project = new Project();
project.Set(Prj.StartDate, new DateTime(2014, 1, 27, 8, 0, 0));

// Add new tasks
var task1 = project.RootTask.Children.Add("Task 1");
var task2 = project.RootTask.Children.Add("Task 2");
task2.Set(Tsk.Duration, task2.ParentProject.GetDuration(16, TimeUnitType.Hour));
var task3 = project.RootTask.Children.Add("Task 3");
task3.Set(Tsk.Duration, task2.ParentProject.GetDuration(24, TimeUnitType.Hour));
var task4 = project.RootTask.Children.Add("Task 4");
task4.Set(Tsk.Duration, task2.ParentProject.GetDuration(16, TimeUnitType.Hour));
var task5 = project.RootTask.Children.Add("Task 5");
task5.Set(Tsk.Duration, task2.ParentProject.GetDuration(16, TimeUnitType.Hour));

// Add links between tasks
project.TaskLinks.Add(task1, task2, TaskLinkType.FinishToStart);
var link23 = project.TaskLinks.Add(task2, task3, TaskLinkType.FinishToStart);

// One day lag
link23.LinkLag = 4800;
project.TaskLinks.Add(task3, task4, TaskLinkType.FinishToStart);
project.TaskLinks.Add(task4, task5, TaskLinkType.FinishToStart);

// Add new tasks
var task6 = project.RootTask.Children.Add("Task 6");
var task7 = project.RootTask.Children.Add("Task 7");
task7.Set(Tsk.Duration, task7.ParentProject.GetDuration(24, TimeUnitType.Hour));
var task8 = project.RootTask.Children.Add("Task 8");
task8.Set(Tsk.Duration, task2.ParentProject.GetDuration(16, TimeUnitType.Hour));
var task9 = project.RootTask.Children.Add("Task 9");
task9.Set(Tsk.Duration, task2.ParentProject.GetDuration(16, TimeUnitType.Hour));
var task10 = project.RootTask.Children.Add("Task 10");

// Add links between tasks
project.TaskLinks.Add(task6, task7, TaskLinkType.FinishToStart);
project.TaskLinks.Add(task7, task8, TaskLinkType.FinishToStart);
project.TaskLinks.Add(task8, task9, TaskLinkType.FinishToStart);
project.TaskLinks.Add(task9, task10, TaskLinkType.FinishToStart);
task6.Set(Tsk.IsManual, true);
task7.Set(Tsk.IsManual, true);
task8.Set(Tsk.IsManual, true);
task9.Set(Tsk.IsManual, true);
task10.Set(Tsk.IsManual, true);

// Save project before and after updating work as completed 
project.Save(OutDir + "RescheduleUncompletedWork_not updated_out.xml", SaveFileFormat.Xml);

// Save project after updating project work as complete only for specified tasks
project.UpdateProjectWorkAsComplete(new DateTime(2014, 1, 28, 17, 0, 0), false, new List<Task> { task10 });
project.Save(OutDir + "RescheduleUncompletedWork_specific_updated_out.xml", SaveFileFormat.Xml);

// Save project after updating all project work as complete
project.UpdateProjectWorkAsComplete(new DateTime(2014, 1, 28, 17, 0, 0), false);
project.Save(OutDir + "RescheduleUncompletedWork_updated_out.xml", SaveFileFormat.Xml);

// Save project after rescheduling uncompleted work only for specified tasks
project.RescheduleUncompletedWorkToStartAfter(new DateTime(2014, 2, 8, 8, 0, 0), new List<Task> { task10 });
project.Save(OutDir + "RescheduleUncompletedWork_specific_rescheduled_out.xml", SaveFileFormat.Xml);

// Save project after rescheduling uncompleted work
project.RescheduleUncompletedWorkToStartAfter(new DateTime(2014, 2, 7, 8, 0, 0));
project.Save(OutDir + "RescheduleUncompletedWork_rescheduled_out.xml", SaveFileFormat.Xml);

See Also


RescheduleUncompletedWorkToStartAfter(DateTime, List<Task>)

Reschedules uncompleted work for a specified list of tasks to start after a specified date.

public void RescheduleUncompletedWorkToStartAfter(DateTime after, List<Task> taskCollection)
ParameterTypeDescription
afterDateTimeThe date to reschedule uncompleted work after.
taskCollectionList`1List<Task> of tasks to reschedule uncompleted work for.

Remarks

Ensure that Project.CanSplitsInProgressTasks flag is set to true before using this method.

Examples

Shows how to update the project and reschedule uncompleted work.

var project = new Project();
project.Set(Prj.StartDate, new DateTime(2014, 1, 27, 8, 0, 0));

// Add new tasks
var task1 = project.RootTask.Children.Add("Task 1");
var task2 = project.RootTask.Children.Add("Task 2");
task2.Set(Tsk.Duration, task2.ParentProject.GetDuration(16, TimeUnitType.Hour));
var task3 = project.RootTask.Children.Add("Task 3");
task3.Set(Tsk.Duration, task2.ParentProject.GetDuration(24, TimeUnitType.Hour));
var task4 = project.RootTask.Children.Add("Task 4");
task4.Set(Tsk.Duration, task2.ParentProject.GetDuration(16, TimeUnitType.Hour));
var task5 = project.RootTask.Children.Add("Task 5");
task5.Set(Tsk.Duration, task2.ParentProject.GetDuration(16, TimeUnitType.Hour));

// Add links between tasks
project.TaskLinks.Add(task1, task2, TaskLinkType.FinishToStart);
var link23 = project.TaskLinks.Add(task2, task3, TaskLinkType.FinishToStart);

// One day lag
link23.LinkLag = 4800;
project.TaskLinks.Add(task3, task4, TaskLinkType.FinishToStart);
project.TaskLinks.Add(task4, task5, TaskLinkType.FinishToStart);

// Add new tasks
var task6 = project.RootTask.Children.Add("Task 6");
var task7 = project.RootTask.Children.Add("Task 7");
task7.Set(Tsk.Duration, task7.ParentProject.GetDuration(24, TimeUnitType.Hour));
var task8 = project.RootTask.Children.Add("Task 8");
task8.Set(Tsk.Duration, task2.ParentProject.GetDuration(16, TimeUnitType.Hour));
var task9 = project.RootTask.Children.Add("Task 9");
task9.Set(Tsk.Duration, task2.ParentProject.GetDuration(16, TimeUnitType.Hour));
var task10 = project.RootTask.Children.Add("Task 10");

// Add links between tasks
project.TaskLinks.Add(task6, task7, TaskLinkType.FinishToStart);
project.TaskLinks.Add(task7, task8, TaskLinkType.FinishToStart);
project.TaskLinks.Add(task8, task9, TaskLinkType.FinishToStart);
project.TaskLinks.Add(task9, task10, TaskLinkType.FinishToStart);
task6.Set(Tsk.IsManual, true);
task7.Set(Tsk.IsManual, true);
task8.Set(Tsk.IsManual, true);
task9.Set(Tsk.IsManual, true);
task10.Set(Tsk.IsManual, true);

// Save project before and after updating work as completed 
project.Save(OutDir + "RescheduleUncompletedWork_not updated_out.xml", SaveFileFormat.Xml);

// Save project after updating project work as complete only for specified tasks
project.UpdateProjectWorkAsComplete(new DateTime(2014, 1, 28, 17, 0, 0), false, new List<Task> { task10 });
project.Save(OutDir + "RescheduleUncompletedWork_specific_updated_out.xml", SaveFileFormat.Xml);

// Save project after updating all project work as complete
project.UpdateProjectWorkAsComplete(new DateTime(2014, 1, 28, 17, 0, 0), false);
project.Save(OutDir + "RescheduleUncompletedWork_updated_out.xml", SaveFileFormat.Xml);

// Save project after rescheduling uncompleted work only for specified tasks
project.RescheduleUncompletedWorkToStartAfter(new DateTime(2014, 2, 8, 8, 0, 0), new List<Task> { task10 });
project.Save(OutDir + "RescheduleUncompletedWork_specific_rescheduled_out.xml", SaveFileFormat.Xml);

// Save project after rescheduling uncompleted work
project.RescheduleUncompletedWorkToStartAfter(new DateTime(2014, 2, 7, 8, 0, 0));
project.Save(OutDir + "RescheduleUncompletedWork_rescheduled_out.xml", SaveFileFormat.Xml);